Royal Decree of 14 January 2013 · Title 5 · Specific provisions for public supply contracts
Article 126. Contract price in the event of delay in performance
Section 1. – Common provisions for all supply contracts
The cost price of the deliveries during a period of delay attributable to the supplier is calculated on the basis of the final price most favourable to the contracting body. To that end, the constituent factors of the prices set for revision are assigned the values determined either by reference to the contractual delivery period, or by reference to the actual delivery period.
Amended byKB 2014-02-07/10, art. 77 (in force 03-03-2014) · KB 2017-06-22/01, art. 2 (in force 30-06-2017)