Royal Decree of 14 January 2013 · Title 5 · Specific provisions for public supply contracts
Article 127. Payments
Section 1. – Common provisions for all supply contracts
The contracting body carries out the verification and the payment of the amount owed to the supplier within the processing period of thirty days from delivery, insofar as the contracting body has the duly drawn-up invoice, as well as the other documents, if any, that are required.
The processing period referred to in the first paragraph is sixty days for contracts awarded by contracting bodies that provide health care and that are specifically recognised for that purpose, but only for the deliveries connected with that specific activity.
An exception is made to the first paragraph in the following cases:
- if the date of receipt of the invoice by the contracting body is not established, the verification and the payment take place within a period of thirty days after delivery;
- if the contracting body receives the invoice before delivery, the verification and the payment take place within a period of thirty days after delivery.
If delivery takes place in several instalments, the processing period begins on the date of delivery, for each partial delivery.
The processing period is suspended in proportion to the number of days:
1° by which the period available to the supplier for submitting its invoice is exceeded, if the contracting body has provided for verification on the basis of the delivery list or of a separate claim for payment and for the submission of the invoice after verification;
2° needed to receive the supplier's reply, where the contracting body, in the context of joint and several liability, has to question it about the actual amount of its social or tax debt as referred to in Article 30bis, § 4, and 30ter, § 4, of the Act of 27 June 1969 revising the Decree-Law of 28 December 1944 on the social security of workers, and in Article 55 of the Code for the amicable and compulsory recovery of tax and non-tax claims.
Amended byKB 2024-08-12/15, art. 10 (in force 01-01-2025)
Previous article
126 — Contract price in the event of delay in performance
Next article
128 — Provisional acceptances