Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts

Article 13. Performance Decree

Section 1. – General framework

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

The contractor is prohibited from entrusting the whole or a part of the contract:

1° to a contractor, supplier or service provider that is in one of the cases referred to in Article 62, first paragraph, 2° to 4°;

2° to a contractor that has been excluded in application of the provisions of the legislation regulating the accreditation of works contractors;

3° where it concerns a contract falling within the scope of Title 2 of the Act, to a contractor, supplier or service provider that is in one of the cases referred to in Article 67 of the Act, except where the contractor, supplier or service provider concerned demonstrates to the contracting body, in accordance with Article 70 of the Act, that it has taken sufficient measures to demonstrate its reliability;

4° where it concerns a contract falling within the scope of Title 3 of the Act, and in so far as the contracting body is also a contracting authority, to a contractor, supplier or service provider that is in one of the cases referred to in Article 67 of the Act, except where the contractor, supplier or service provider concerned demonstrates to the contracting body, in accordance with Article 70 of the Act, that it has taken sufficient measures to demonstrate its reliability;

5° where it concerns a contract falling within the scope of the Defence and Security Act, to a contractor, supplier or service provider that is in one of the cases referred to in Article 63 of the royal decree for defence and security.

The contractor is moreover prohibited from allowing these persons to take part in the management or supervision of the whole or a part of the contract.

Any infringement of this prohibition may give rise to the application of an ex officio measure.

Amended byKB 2017-06-22/01, art. 14 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.