Royal Decree of 14 January 2013 · Title 1 · General provisions
Article 9. Derogations and unfair terms
§ 1 In so far as they are applicable in accordance with Articles 5, 6, §§ 1 to 3, and Article 7, no derogation may be made from the provisions of:
1° Chapter 1;
The first paragraph, 3°, does not, however, apply to the contracts referred to in paragraph 4, third paragraph.
§ 2 Except as regards the possibilities of derogation referred to in paragraph 3/1, the procurement documents may not derogate from the time limit referred to in Articles 95, §§ 3 and 4, 127 and 160. Any provision to the contrary shall be deemed unwritten. Without prejudice to paragraphs 1 and 4, this paragraph does not, however, apply provided that each of the following conditions is met:
1° the procurement documents expressly provide for a longer processing period;
2° this derogation is objectively justified on the basis of the particular nature or characteristics of the contract;
3° the processing period is in no case longer than sixty days;
4° this extension does not constitute a grossly unfair term towards the contractor as referred to in paragraph 3.
§ 3 A contractual provision or a practice that constitutes a grossly unfair term towards the contractor shall be deemed unwritten with regard to the processing date or period, the rate of interest for late payment or the compensation for recovery costs.
In assessing whether a contractual provision or a practice constitutes a grossly unfair term towards the contractor, all circumstances are taken into account, in particular:
1° any substantial departure from good commercial practice that is contrary to good faith and fair dealing;
2° the nature of the works, supplies or services;
3° whether the contracting body has objective reasons to derogate from the processing period referred to in Articles 95, §§ 3 and 4, 127 and 160.
§ 3/1 For public contracts awarded by contracting bodies that provide health care and are specifically recognised for that purpose, albeit only for contracts connected with that specific activity, the contracting body may, by means of a provision to that effect in the procurement documents, derogate from the time limits referred to in Articles 95, §§ 3 and 4, 127 or 160 and provide for a separate verification period of at most thirty days and a separate payment period of sixty days, the latter period starting to run only from the date on which the verification ends, in so far as the contracting body has the duly drawn-up invoice and the other required documents. In that case, the contracting body shall determine in the procurement documents the duration of the verification period, which may not exceed thirty.
The possibility of derogation referred to in the first paragraph may be used only in so far as the procurement documents actually provide for a verification procedure. The verification period referred to in the first paragraph may moreover not be used merely to arrive at a longer overall payment period.
Where the contracting body makes use of the possibility of derogation referred to in the first paragraph for a works contract, the verification period starts to run from the date on which the contracting body receives the claim for payment and the detailed statement of the works carried out as referred to in Article 95, § 1. Where the contracting body makes use of the possibility of derogation referred to in the first paragraph for a supply contract, the verification period starts to run from the delivery established in accordance with Article 120. Where the contracting body makes use of the possibility of derogation referred to in the first paragraph for a service contract, the verification period starts to run from the date of the complete or partial completion of the services established in accordance with the provisions of the procurement documents.
Where the aforementioned possibility of derogation is applied, in the event that the applicable verification period is exceeded, the payment period is reduced in proportion to the number of days by which the verification period is exceeded. Conversely, the payment period is suspended in proportion to the number of days:
1° by which the time limit available to the contractor to submit its invoice is exceeded;
2° needed to receive the contractor's reply, where the contracting body, in the context of joint and several liability, must question it about the actual amount of its social or tax debt as referred to in Article 30bis, § 4, and 30ter, § 4, of the Act of 27 June 1969 revising the Decree-Law of 28 December 1944 on social security for workers, as well as in Article 55 of the Code of amicable and compulsory recovery of tax and non-tax claims.
§ 4 Derogation from mandatory provisions other than those referred to in paragraphs 2 and 3 of this Article is permitted only in duly justified cases, in so far as the specific requirements of the contract make this necessary. Derogation from Articles 38/7, 38/9, §§ 1 to 3 and 38/10, §§ 1 to 3 is, however, possible in duly justified cases without the necessity of the derogation having to be demonstrated.
The reasons for the derogations need not be included in the contract specifications. The derogations from Articles 10, 12, 13, 18, 25 to 30, 38/9, §§ 1 to 3, 38/10, §§ 1 to 3, 44 to 61, 66, 68, 70 to 73, 78, 79 to 81, 84, 86, 96, 121, 123, 151 and 154 must, however, be expressly reasoned in the contract specifications. If this reasoning is absent, the derogation shall be deemed unwritten. This sanction does not apply in the following cases:
1° in the case of an agreement signed by the parties;
2° ...
The first and second paragraphs do not apply to contracts that relate to the financing, the design and the execution of works and, where appropriate, to any service provision in that connection. For these contracts, derogation is permitted from mandatory provisions other than those referred to in paragraphs 2 and 3, provided that the fourth paragraph is complied with.
For all contracts, the list of the provisions from which derogation is made is expressly stated at the beginning of the contract specifications.
Amended byKB 2014-05-22/03, art. 5 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2017-06-22/01, art. 9 (in force 30-06-2017) · KB 2018-04-15/01, art. 7 (in force 28-04-2018) · KB 2024-08-12/15, art. 3 (in force 01-01-2025)
Cross-references
This article refers to
Previous article
8 — Where ... by taking into account a variant or option a supply contract has…
Next article
10 — Use of electronic means