Royal Decree of 14 January 2013 · Title 5 · Specific provisions for public supply contracts

Article 131. Full acceptance at the place of delivery without partial acceptance at the place of production

Section 2. – Supplementary provisions for supply contracts involving purchase

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 Where provisional acceptance takes place entirely at the place of delivery, the contracting body has one of the following periods to examine and test the deliveries and to communicate its decision to accept or refuse them:

1° thirty days;

2° sixty days where the procurement documents provide that the acceptance operations require the involvement of a laboratory.

This period begins on the day after that on which the goods arrive at the place of delivery, on condition that the contracting body has been given the delivery list or invoice referred to in Article 118, § 2. The period of thirty days provided for in Article 127 is included in it.

§ 2 Where deliveries are rejected, the supplier is notified thereof by registered mail or by electronic means that guarantee the exact date of dispatch in a comparable manner, and must remove them within a period of fifteen days.

After expiry of that period, the contracting body is released from all liability for the deliveries not removed. They may be sent back of the contracting body's own motion and at the supplier's expense.

§ 3 The contracting body may set a final date for the removal of the rejected deliveries. It may make use of that right only if at least thirty days have elapsed between the day of notification and the day set for removal.

For each day of delay after the final date set, a penalty may be applied in accordance with Article 45.

Amended byKB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2024-08-12/15, art. 12 (in force 01-01-2025)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.