Royal Decree of 14 January 2013 · Title 6 · Specific provisions for public service contracts
Article 155. Measures taken of its own motion
§ 1 Where measures are taken of the contracting body's own motion in the form of performance in-house or of a contract for the account of the defaulting party, the additional costs are calculated exclusively on the services that the defaulting service provider was bound to carry out and that were actually ordered from the new service provider or carried out in-house. However, no account is taken of the price revisions referred to in Article 38/7, § 2, nor of the reductions for loss of value referred to in Article 71 of this Decree, which could have altered the prices of the defaulting service provider or of the new service provider. The prices that are taken into account for the calculation of the additional costs are, where applicable, increased by value added tax.
Fines for late performance continue to run at the expense of the service provider who has been put in default until the actual date of performance of the services and, in the case of a contract for the account of the defaulting party, at the latest until the expiry of the period for performance of the contracting body's own motion.
§ 2 Services performed for the account of the defaulting party are inspected and accepted in accordance with the requirements of the original contract.
The service provider that has been put in default is duly notified of the place where and the date on which the tests will be carried out. It may be present or be represented there, unless the new service provider objects to this where the inspection operations have to take place in its establishments. In that case the service provider in default may demand communication of the result of the verification and the inspection.
§ 3 The service provider put in default also bears the costs of awarding the contract for its account. Regardless of the method of award used for the contract, these costs are set at one per cent of the original contract sum of that contract, with a maximum of fifteen thousand euro.
Amended byKB 2017-06-22/01, art. 47 (in force 30-06-2017)