Royal Decree of 14 January 2013 · Title 6 · Specific provisions for public service contracts
Article 154. Penalties for delay
Fines for late performance are calculated at the rate of 0.1 per cent per day of delay, with a maximum of seven and a half per cent, of the value of all or part of the services whose performance took place with the same delay. Where applicable, the procurement documents state the basis of calculation of the fines.
Where the performance period constitutes an award criterion of the contract, the procurement documents determine the method of calculating the penalties for delay for the services performed with the same delay. In that case the procurement documents may increase the above-mentioned percentage to a maximum of ten per cent. This percentage is set in proportion to the relative importance of the award criterion relating to the performance period. If the method of calculation is not stated in the procurement documents, that of the first paragraph applies.
The value of the services is calculated on the basis of the original contract amount, taking account of the modifications made but not of the price revisions referred to in Article 38/7, § 2, and of the reductions for loss of value referred to in Article 71 of this Decree.
Fines for late performance whose total amount does not reach seventy-five euro per contract are not charged.
If the contract consists of several parts or phases, each with its own performance period and its own amount, each of the parts is treated as a separate contract for the application of the fines.
If the contract does not consist of parts or phases within the meaning of the fifth paragraph, but the procurement documents set partial performance periods without designating them as binding, those periods must be regarded as mere forecasts for the performance of the contract and, for the application of the fines, only the final period is taken into account. If, on the other hand, the procurement documents state that the partial performance periods are mandatory, failure to observe them is penalised by special fines provided for that purpose in the procurement documents or, if there is no such provision, by fines calculated in accordance with the provision in the first paragraph.
Amended byKB 2017-06-22/01, art. 46 (in force 30-06-2017)
Previous article
153 — Services that do not comply with the provisions and conditions of the contract…
Next article
155 — Measures taken of its own motion
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.