Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 28. Adjustment of the security
Section 3. – Financial guarantees
Where the security, for whatever reason, is no longer adequate, in particular as a result of ex officio deductions, additional services or modifications decided by the contracting body, which increase or decrease the original amount of the contract by more than twenty per cent, the security is restored to the original amount or adjusted upwards or downwards.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)