Article 33. Release of the security
Section 3. – Financial guarantees
Where the contracting body accepts the provisional and/or final acceptance, the security is released by half or in full in accordance with Articles 93, 133, 144 and 158, even if the contractor has not submitted a request to that effect.
To the extent that the security can be released, the contracting body shall, within fifteen days after the provisional and/or final acceptance, grant a release to the Deposit and Consignment Office, to the public institution performing a similar function, to the credit institution or to the insurance undertaking, as the case may be. After that period, the contractor is entitled to payment:
1° either of interest which, in the case of a deposit in cash or public funds, is calculated in accordance with Article 69, § 1, on the amounts deposited, possibly reduced by the interest paid by the Deposit and Consignment Office or by a public institution performing a similar function. The application for return of the security counts in that case as a claim for payment of that interest;
2° or of the costs incurred for maintaining the security, in the case of collective security or of a guarantee granted by a credit institution or an insurance undertaking.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2023-09-04/06, art. 2 (in force 01-11-2023)
Previous article
32 — Transfer of the security
Next article
33/1 — In the separate electronic form drawn up for that purpose by the Federal Public…
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.