Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 93. Release of the guarantee
Section 1. – Provisions applicable to all works contracts
Where there are two acceptances, a provisional and a final one, the guarantee is released in halves: one half after the provisional acceptance of the entire contract, the other half after the final acceptance, in both cases after deduction of any sums owed by the contractor to the contracting body.
Where provision is made for only a single acceptance, the release takes place in one go after that acceptance.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)
Cross-references
Referred to by
Previous article
92 — A construction that does not satisfy the provisions or conditions of the…
Next article
94 — Contract price in the event of delay in performance
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.