Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 38/18. Verification of accounting documents
Section 5. – Modifications of the contract
Where the contractor requests the application of a contractual modification clause with a view to obtaining damages or a revision of the contract, the contracting body has the right to check the accounting documents on the spot.
Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)
Previous article
38/17 — The contracting body must, no later than ninety days following the date of…
Next article
38/19 — Publication