Article 38/6. Performance Decree

Section 5. – Modifications of the contract

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

A modification of a contract or a framework agreement during its term is to be regarded as substantial where it renders the contract or framework agreement materially different in character from the original contract or framework agreement.

A modification is to be regarded as substantial where at least one of the following conditions is met:

1° the modification introduces conditions which, had they been part of the initial award procedure, would have allowed for the admission of candidates other than those initially selected or for the award of the contract to a tenderer other than the one initially selected, or would have attracted additional participants in the award procedure;

2° the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner that was not provided for in the original contract or framework agreement;

3° the modification considerably extends the scope of the contract or framework agreement;

4° a new contractor replaces the contractor to which the contracting body had initially awarded the contract in cases other than those referred to in Article 38/3.

Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.