Article 42. Prior inspection

Section 6. – Checks and supervision of the contract

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 As a rule, products may not be incorporated before they have been approved by the supervising official or his representative.

The inspection may be carried out at different stages of production.

Products that do not satisfy the prescribed inspection tests at a given stage are regarded as not being in a condition to be submitted for inspection.

At the request of the contractor, the contracting body shall examine, in accordance with the provisions of the procurement documents, to what extent the products meet the quality requirements or at least comply with the rules of good workmanship and the conditions of the contract.

If the verification involves the destruction of certain products, the contractor shall replace them at his own expense. The procurement documents specify how many products will be destroyed.

Where the contracting body finds that the product submitted for inspection is not in a condition to be examined, the contractor's request is regarded as non-existent. The request is made again as soon as the product is ready for inspection.

§ 2 Products that were previously inspected may still be rejected later. They shall be replaced immediately by the contractor where a new examination shows, whether before they are put into use, during their incorporation, or after performance of the contract but before final acceptance, that they exhibit defects or damage which were not noticed during the first examination, or damage that has arisen afterwards.

Any replacement of the defective products does not affect the contractor's obligations arising from the provisions of Articles 64, 65 and 92.

§ 3 For the notification of approval or refusal, the contracting body has the following periods, starting on the day of receipt of the request to proceed with the inspection:

1° thirty days;

2° sixty days if the inspection operations take place in a laboratory.

The procurement documents may, however, provide for shorter periods.

Where the inspection of the products must take place outside Belgian territory, the period is extended by the number of days necessary for the outward and return journey of the inspectors.

If these periods are exceeded through the fault of the contracting body, the performance period is extended accordingly by operation of law. This extension excludes any right to damages.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.