Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts

Article 92. Performance Decree

Section 1. – Provisions applicable to all works contracts

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 A construction that does not satisfy the provisions or conditions of the contract or that has not been executed in accordance with the rules of workmanship and the art of building shall be demolished and rebuilt by the contractor. Failing this, this is done ex officio on the order of the contracting body at his expense and risk, in accordance with the means of action laid down in Article 87. The contractor moreover exposes himself to fines and penalties for failure to comply with the provisions and conditions of the contract.

The contracting body may in the same way oblige the contractor to demolish and rebuild the construction or parts of it in which products that were not accepted were incorporated or which were executed during a prohibited period. If necessary, it shall act ex officio at the expense and risk of the contractor.

§ 2 Where the construction is completed on the date set for that purpose and insofar as the results of the inspections and of the prescribed tests are known, a report of provisional acceptance or of refusal of acceptance, as the case may be, is drawn up within fifteen days after the above-mentioned date.

Where the construction is completed before or after that date, the contractor shall notify the supervising official thereof by registered mail or by electronic means which similarly guarantees the exact date of dispatch and shall at the same time request provisional acceptance. Within fifteen days after the date on which the contractor's request is received and insofar as the results of the inspections and of the prescribed tests are known, a report of provisional acceptance or of refusal of acceptance is drawn up.

...

A construction that has been found to be in a state of provisional acceptance is, until proof to the contrary, presumed to have been in that state on the date on which it was to be completed or, as regards the cases of the second paragraph, on the date of actual completion stated by the contractor in his registered mail or in his electronic dispatch which similarly guarantees the exact date of dispatch.

The guarantee period starts on the date of provisional acceptance. If the procurement documents do not stipulate a guarantee period, it is set at one year.

§ 3 Within the fifteen days before the day on which the guarantee period expires, a report of final acceptance or of refusal of acceptance, as the case may be, is drawn up.

In the latter case, the contractor must subsequently notify the contracting body, by registered mail or by electronic means which similarly guarantees the exact date of dispatch, that the whole of the construction has been put in a state of final acceptance. The construction is accepted within fifteen days following receipt of that notification by the contracting body.

A construction that has been found to be in a state of final acceptance is, until proof to the contrary, presumed to have been in that state on the end date of the guarantee period or, as regards the cases of the second paragraph, on the date of final acceptance stated by the contractor in his registered mail or in his electronic dispatch which similarly guarantees the exact date of dispatch.

§ 4 The verification with a view to the provisional or final acceptance of the construction takes place in the presence of the contractor, or after he has been duly summoned, at least seven days before the day of acceptance, by registered mail or by electronic means which similarly guarantees the exact date of dispatch.

Where, as a result of adverse weather conditions, the state of the construction cannot be recorded during the fifteen-day period laid down for provisional or final acceptance, that impossibility shall be established by report after the contractor has been summoned, and the report of acceptance or of refusal of acceptance shall be drawn up within fifteen days after the day on which the impossibility ceased to exist.

The contractor may not invoke those circumstances to evade the obligation to present the construction in a good state for acceptance.

The construction is considered completed only after the contractor has had every deposit, obstruction or alteration of the state of the site made for the performance of the contract removed.

Amended byKB 2014-05-22/03, art. 8 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by