Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 46. Penalties for delay
Section 7. – Remedies of the contracting body
Penalties for delay are independent of the penalties referred to in Article 45. They are payable without notice of default by the mere expiry of the performance period, without a report being drawn up, and are applied by operation of law for the total number of days of delay.
Without prejudice to the application of penalties for delay, the contractor shall, where applicable, indemnify the contracting body against any damages which the latter owes to third parties on account of his delay in the performance of the contract.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)
Previous article
45 — Penalties
Next article
46/1 — Value added tax is not taken into account in the calculation basis of the…