Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts

Article 46. Penalties for delay

Section 7. – Remedies of the contracting body

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

Penalties for delay are independent of the penalties referred to in Article 45. They are payable without notice of default by the mere expiry of the performance period, without a report being drawn up, and are applied by operation of law for the total number of days of delay.

Without prejudice to the application of penalties for delay, the contractor shall, where applicable, indemnify the contracting body against any damages which the latter owes to third parties on account of his delay in the performance of the contract.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.