Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 66. Performance Decree
Section 11. – General payment conditions
§ 1 The price of the contract is paid either in one go after its full performance, or by part payments as performance progresses and in accordance with the arrangements laid down in the procurement documents.
As soon as the performance of a contract has progressed to the point that it gives entitlement to payment, a report thereof is drawn up by the contracting body. The contractor must, however, submit a claim before he can be paid.
§ 2 Where, on the order or through the act of the contracting body, performance of the contract is suspended for a period of at least thirty days, the contractor receives a part payment in proportion to the services performed.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)
Cross-references
Referred to by
Previous article
65 — The guarantee provided by the contractor is governed by the provisions of this…
Next article
66/1 — In the electronic form drawn up for that purpose by the Federal Public Service…
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.