Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 68. Payment in the event of opposition to payment or garnishment by a third party
Section 11. – General payment conditions
In the event of opposition to payment or of a protective garnishment by a third party against the contractor, the processing period is suspended .... The suspension ends on the day on which the contracting body is informed that the obstacle to payment has been lifted.