Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 72. Set-off
Section 11. – General payment conditions
Any amount owed to the contracting body in the context of the performance of the contract shall first be deducted from the amounts payable to the contractor for whatever reason and subsequently from the surety.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)