Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts

Article 90. Finds during the works

Section 1. – Provisions applicable to all works contracts

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

Any find of any significance made during excavation or demolition work shall be notified without delay to the contracting body.

Pending a decision of the contracting body and without prejudice to his right to damages, the contractor shall interrupt the performance of the works in the immediate vicinity of the find and prohibit all access.

Works of art, antiquities, natural history objects, numismatic objects or other objects having scientific value, as well as rare and valuable objects found during excavation or demolition work, shall, pending the determination of ownership rights on the basis of the applicable legislation, be kept at the disposal of the supervising official or of his representative, unless otherwise provided in the procurement documents.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)