Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 91. Acceptances and guarantee
Section 1. – Provisions applicable to all works contracts
Through provisional acceptance, the contracting body takes possession of the whole of the construction carried out by the contractor.
Before provisional acceptance, the contracting body may, where it considers this desirable, take possession of the different parts of the construction as they are completed, provided that an inventory of the condition of the premises is drawn up thereof.
Full or partial taking possession of the construction by the contracting body cannot count as provisional acceptance.
As soon as the contracting body has taken possession of the construction in whole or in part, the contractor is, however, no longer obliged to repair damage due to its use.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)
Previous article
90 — Finds during the works
Next article
92 — A construction that does not satisfy the provisions or conditions of the…