Article 91. Acceptances and guarantee

Section 1. – Provisions applicable to all works contracts

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

Through provisional acceptance, the contracting body takes possession of the whole of the construction carried out by the contractor.

Before provisional acceptance, the contracting body may, where it considers this desirable, take possession of the different parts of the construction as they are completed, provided that an inventory of the condition of the premises is drawn up thereof.

Full or partial taking possession of the construction by the contracting body cannot count as provisional acceptance.

As soon as the contracting body has taken possession of the construction in whole or in part, the contractor is, however, no longer obliged to repair damage due to its use.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)