Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 94. Contract price in the event of delay in performance
Section 1. – Provisions applicable to all works contracts
The price of works carried out during a period of delay attributable to the contractor is determined as follows, on the basis of the calculation method that is most favourable to the contracting body:
1° either by assigning to the constituent factors of the prices that are designated in the contract for revision the values that applied during the period of delay concerned;
2° or by assigning to each of those factors an average value (E) determined by the following formula:
(Formula not reproduced for technical reasons, see Belgian Official Gazette of 14-02-2013, p. 8840)
where:
e1, e2,... en, the successive values of the factor concerned during the contractual period, extended where applicable to the extent that the delay was not attributable to the contractor;
t1, t2,.. tn, the corresponding duration of each value, expressed in months of thirty days. A part of a month and the duration of suspensions in the performance of the contract are not taken into account.
The value of E is calculated to the second decimal place.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)