Act of 17 June 2013 · Title II · Reasoning, information and remedies for public contracts falling under the Public Procurement Act and for concessions falling under the Concessions Act
Article 29/1. Remedies Act
Chapter 2. – Contracts and concessions not reaching the European thresholds — Section 2. – Reasoned decision, information to candidates, participants and tenderers and standstill period
§ 1 For contracts whose expenditure to be approved, excluding value added tax, does not exceed the applicable threshold amounts referred to in Article 29, § 1, first paragraph, the contracting body draws up a reasoned decision in the cases below:
1° when it decides on the selection of candidates where the procedure includes a first phase involving the submission of requests to participate;
2° when it awards the contract, regardless of the procedure;
3° when it refrains from awarding the contract and possibly decides to initiate a new award procedure.
In addition, the contracting body communicates the following:
1° where the award procedure includes a first phase involving the submission of requests to participate, and immediately after taking the reasoned selection decision, to each candidate not selected, that he has not been selected;
2° immediately after taking the award decision, to each candidate or tenderer not selected, that he has not been selected, to each tenderer whose tender has been rejected or not chosen, that his tender has been rejected or not chosen, and to the tenderer chosen, that he has been chosen.
Within a period of thirty days from the date of dispatch of the information referred to in the second paragraph, the candidate or tenderer concerned may request in writing that the following additional information be communicated to him:
1° each candidate or tenderer not selected: the reasons for his non-selection, in the form of an extract from the reasoned decision;
2° each tenderer whose tender has been rejected: the reasons for the rejection, in the form of an extract from the reasoned decision;
3° each tenderer whose tender has not been chosen and the contractor: the reasoned decision.
The contracting body communicates this additional information within a period of fifteen days from the date of receipt of the request to that effect.
The contracting body may, however, make use of the possibilities provided for in Article 8, § 1, first paragraph, and, as the case may be, add the reasons referred to in the third paragraph to the information. The reasoned decision is attached to the information where the contracting body makes Article 11, first paragraph, applicable, in accordance with Article 30, § 1, second paragraph.
§ 2 For the contracts referred to in § 1, first paragraph, the contracting body, immediately after taking the decision to refrain from awarding the contract and, where applicable, to initiate a new award procedure, communicates this decision to each candidate or tenderer concerned.
Within a period of thirty days from the date of dispatch of this information, the candidate or tenderer concerned may request in writing that the reasoned decision be communicated to him.
The contracting body communicates the reasoned decision within a period of fifteen days from the date of receipt of the request to that effect.
§ 3 Where the contracting body, for the contracts referred to in § 1, first paragraph, decides on the qualification or the withdrawal of the qualification in the context of a qualification system, it draws up a reasoned decision. Immediately after taking this decision, the contracting body communicates this qualification or withdrawal to each candidate concerned.
Within a period of thirty days from the date of dispatch of this information, the candidate concerned may request in writing that the reasons for this decision be communicated to him, in the form of an extract from the reasoned decision.
The contracting body communicates the extract from the reasoned decision within a period of fifteen days from the date of receipt of the request to that effect.
§ 4 Where the contracting body, for the contracts referred to in § 1, first paragraph, decides to use the competitive dialogue, it draws up a reasoned decision.
In addition, a reasoned decision is drawn up, for the contracts referred to in § 1, first paragraph, where the contracting body decides, in the context of the competitive dialogue, on the solution or solutions that can meet its needs and requirements. Immediately after taking this decision, the contracting body communicates it to each participant concerned. Within a period of thirty days from the date of dispatch of this information, the participant concerned may request in writing that the reasoned decision be communicated to him. The contracting body communicates the reasoned decision within a period of fifteen days from the date of receipt of the request to that effect.
Where the contracting body decides, for the contracts referred to in § 1, first paragraph, in the context of the competitive dialogue, to declare the dialogue closed, it also draws up a reasoned decision thereon. Immediately after taking this decision, the contracting body communicates it to each participant concerned. Under the same arrangements as referred to in the previous paragraph, the participant concerned may then request in writing that the reasoned decision be communicated to him.
§ 5 Where the contracting body, for the contracts referred to in § 1, first paragraph, in the context of a dynamic purchasing system, decides not to admit a participant, it draws up a reasoned decision. Immediately after taking this decision, the contracting body communicates it to each participant concerned. Within a period of thirty days from the date of dispatch of this information, the participant concerned may request the contracting body in writing to communicate to him the reasons for this decision, in the form of an extract from the reasoned decision.
The contracting body provides the extract from the reasoned decision within a period of fifteen days from the date of receipt of the request to that effect.
§ 6 The contracting body makes the communications of the decisions and reasoning concerned referred to in §§ 1 to 5 by fax, by e-mail or via the electronic platforms referred to in Article 14, § 7, of the Public Procurement Act and, on the same day, by registered mail.
The communications referred to in §§ 1 to 5 set out the remedies, their time limits and the competent bodies, at least by means of an express reference to Articles 14, 15, 23 and 24.
If this information is missing, the time limit referred to in Article 23, § 2, for bringing the action for annulment starts four months after the reasoning has been communicated.
§ 7 §§ 1 to 6 do not apply to contracts of limited value as referred to in Articles 92 and 162 of the Public Procurement Act.
§ 8 Article 4, third paragraph, and Article 10 apply to the contracts referred to in § 1, first paragraph.
Amended byW 2017-02-16/19, art. 38 (in force 30-06-2017)
Previous article
29 — For contracts whose expenditure to be approved, excluding value added tax…
Next article
29/2 — For the concessions referred to in this Chapter, only Articles 4/1, 5/1, 7, 8…
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.