Act of 17 June 2013 · Title III · Reasoning, information and remedies for public contracts falling under the Defence and Security Act

Article 38. Remedies Act

Chapter 1. – Contracts that reach the European thresholds — Section 2. – Reasoned decision

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

The decision referred to in Article 37 serves as a record and shall be forwarded, at its request, to the European Commission. Where applicable, this record shall be supplemented with:

1° an indication of the part of the contract or of the framework agreement that the beneficiary intends or is obliged to subcontract;

2° the justification, in the event of a negotiated procedure without publication, for exceeding the duration of five years for contracts relating to additional supplies as referred to in Article 25, 3°, a), second paragraph, of the Defence and Security Act or for contracts consisting of the repetition of similar works or services as referred to in Article 25, 4°, b), second paragraph, of the same Act;

3° the justification, in the event of a negotiated procedure without publication, for exceeding the ceiling of 50 % of the amount of the main contract for the additional works or services as referred to in Article 25, 4°, a), second paragraph, of the Defence and Security Act;

4° an indication of the reasons why the duration of the framework agreement is longer than seven years.

Amended byW 2017-02-16/19, art. 4 (in force 30-06-2017)

Cross-references

This article refers to

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.