Act of 17 June 2013 · Title III · Reasoning, information and remedies for public contracts falling under the Defence and Security Act

Article 39. Remedies Act

Chapter 1. – Contracts that reach the European thresholds — Section 3. – Information to candidates, participants and tenderers

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 Where the procedure includes a first stage with the submission of requests to participate, the contracting body shall, immediately after the reasoned selection decision has been taken, communicate the following to each candidate not selected:

1° the reasons for his non-selection, in the form of an extract from this decision;

2° in the event of a limitation of the number of candidates selected on the basis of a ranking, the reasoned selection decision.

The invitation to submit a tender may not be sent to the selected candidates before this information has been dispatched.

§ 2 In the event of the establishment and operation of a qualification system, the contracting body shall, immediately after the reasoned qualification decision has been taken, communicate to each non-qualified candidate the reasons for his non-qualification, in the form of an extract from this decision. This communication shall be made without delay and at the latest within fifteen days of the date of the decision.

Prior to the withdrawal of the qualification of a contractor, supplier or service provider, the contracting body shall communicate to him, at least fifteen days before the date set for the withdrawal of the qualification, its intention and the reasons justifying this withdrawal, as well as the possibility to submit his comments within the same period.

§ 3 In the event of a competitive dialogue, the contracting body shall, immediately after the decision on the solution or solutions that can meet its needs and requirements has been taken, communicate the reasoned decision for this choice to the participants whose solution has not been chosen.

Amended byW 2017-02-16/19, art. 48 (in force 30-06-2017)

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.