Skip to content

Act of 17 June 2013 · Title III · Reasoning, information and remedies for public contracts falling under the Defence and Security Act

Article 52. Remedies Act

Chapter 1. – Contracts that reach the European thresholds — Section 5. – Review procedures — Subsection 4. – Declaration of ineffectiveness

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The review body may decide not to declare a contract ineffective, even though it was unlawfully concluded for the reasons referred to in Article 49, if, after examining all relevant aspects, it considers that overriding reasons relating to a general interest, relating in the first place to defence or security interests, require that the contract remain effective.

In that case, the review body shall instead impose alternative penalties as referred to in Article 54.

As regards not declaring a contract ineffective, economic interests may be considered as overriding reasons only if, in exceptional circumstances, ineffectiveness would lead to disproportionate consequences.

However, economic interests directly linked to the contract concerned cannot constitute overriding reasons relating to a general interest. Economic interests directly linked to the contract include, among others, the costs resulting from the delay in performing the contract, the costs of a new procedure, the costs resulting from the change of the economic operator performing the contract, and the costs of legal obligations resulting from ineffectiveness.

In any event, a contract may not be considered ineffective if the consequences of that ineffectiveness would seriously endanger the very existence of a wider defence or security programme that is essential for the security interests of a Member State.

§ 2 The declaration of ineffectiveness referred to in Article 49, first paragraph, 3°, does not apply if the contracting body:

- considers that the award of the contract is in accordance with Article 138, second paragraph, 2°, of the Royal Decree on the award of public contracts and certain works, supply and service contracts in the field of defence and security of 23 January 2012 and;

- voluntarily makes Article 43 applicable;

- has complied with the provisions of Article 40, § 1, immediately after taking the award decision in accordance with Article 36, first paragraph, 6°.

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.