Skip to content

Act of 17 June 2013 · Title III · Reasoning, information and remedies for public contracts falling under the Defence and Security Act

Article 49. Remedies Act

Chapter 1. – Contracts that reach the European thresholds — Section 5. – Review procedures — Subsection 4. – Declaration of ineffectiveness

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

At the request of any interested party, the review body shall declare the concluded contract ineffective in each of the following cases:

1° without prejudice to Article 50, where the contracting body has concluded a contract without prior European publication, although European Union law on public contracts or the legislation on public contracts nevertheless requires it;

2° where the contracting body has concluded the contract without observing the period referred to in Article 43, first paragraph, or without waiting until the review body, where applicable of first instance, has ruled either on the action for suspension or on the action for interim measures, where:

a) a tenderer has been unable, as a result of this infringement, to bring or complete an action for suspension as referred to in Article 43, second paragraph, and

b) this infringement is accompanied by an infringement of European Union law on public contracts or of the legislation on public contracts, as a result of which the tenderer's chances of obtaining the contract were adversely affected;

3° where the contracting body has concluded the contract on the basis of a framework agreement without all the conditions having already been laid down in that framework agreement, where there is an infringement of the procedural rules laid down in that regard by the King in accordance with the Directive.

The contracting body and the contractor shall be parties to this review procedure. To that end, the contracting body shall communicate the identity of the contractor as soon as the person bringing the action so requests.

The action for a declaration of ineffectiveness of the contract may be brought together with the action for annulment referred to in Article 46 or separately.

Amended byW 2017-02-16/19, art. 4 (in force 30-06-2017) · W 2017-02-16/19, art. 54 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.