Text of the consolidated version in force from 17 February 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 When setting the time limits for requests to participate and for the receipt of tenders, the contracting authority shall take account of the complexity of the contract and of the time needed for the preparation of tenders, without prejudice to the minimum time limits laid down in Articles 36 to 41.

§ 2 Where tenders can be drawn up only after a site visit or after on-the-spot consultation of the documents on which those procurement documents are based, the time limits for the receipt of tenders, which are longer than the minimum time limits laid down in Articles 36 to 41, shall be set so that all economic operators concerned have the opportunity to take cognisance of all the information needed to draw up the tenders.

§ 3 The contracting authority shall extend the time limits for the receipt of tenders, so that all economic operators concerned can have access to all the information needed to draw up the tenders, in the following cases:

1° where, for whatever reason, additional information, although requested in good time by the economic operator, has not been provided at the latest six days before the time limit set for the receipt of tenders. In the case of the accelerated procedure referred to in Articles 36, § 3, and 37, § 4, this period is four days;

2° where the procurement documents have been significantly modified.

The length of the extension shall be proportionate to the importance of the information or modification.

Where the additional information has not been requested in good time or its importance for the preparation of tenders is insignificant, the contracting authority need not extend the time limits.

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.