Act of 17 June 2016 · Title 2 · Public contracts in the classical sectors
Article 41. Use of the simplified negotiated procedure with prior publication
Chapter 2. – Award procedures
§ 1 Public contracts may be awarded by simplified negotiated procedure with prior publication only in the following cases:
1° for supplies and services whose estimated amount is below the relevant threshold for European publication;
2° for works whose estimated amount is below EUR 750,000.
§ 2 In a simplified negotiated procedure with prior publication, any interested economic operator may, in response to a contract notice, submit a tender.
The time limit for the receipt of tenders shall be at least twenty-two days from the date of dispatch of the contract notice. Article 37, §§ 3 to 5, shall apply.
The tender must be accompanied by the information for selection requested by the contracting authority.
§ 3 With a view to improving their content, the contracting authority may negotiate with the tenderers on the initial tenders and all subsequent tenders submitted by them, except for the final tenders.
The minimum requirements and the award criteria shall not be negotiated.
§ 4 During the negotiations, the contracting authority shall ensure the equal treatment of all tenderers. To that end, it shall not provide discriminatory information which may give some tenderers an advantage over others. It shall inform in writing all tenderers whose tenders have not been eliminated pursuant to paragraph 5 of any changes to the technical specifications or other procurement documents, other than those setting out the minimum requirements. Following those changes, the contracting authority shall provide sufficient time for tenderers to modify and resubmit their tenders, where necessary.
In accordance with Article 13, the contracting authority shall not reveal to the other participants confidential information communicated by a candidate or tenderer participating in the negotiations without that person's written consent. Such consent shall not take the form of a general waiver but shall be given with reference to the intended communication of specific information.
§ 5 The simplified negotiated procedure with prior publication may take place in successive stages in order to reduce the number of tenders to be negotiated by applying the award criteria specified in the contract notice or in another procurement document. The contracting authority shall indicate in the contract notice or in another procurement document whether it will use that option.
§ 6 Where the contracting authority intends to conclude the negotiations, it shall inform the remaining tenderers and set a common deadline to submit any new or revised tenders. The contracting authority shall verify that the final tenders comply with the minimum requirements and with Article 66, § 1, evaluate the final tenders on the basis of the award criteria and award the contract pursuant to Articles 79 to 84.
Where the contracting authority decides not to negotiate, the initial tender shall be deemed to be the final tender.
§ 7 The King may determine the further additional procedural rules applicable to the simplified negotiated procedure with prior publication.
On this site
Previous article
40 — Innovation partnership
Next article
42 — Use of the negotiated procedure without prior publication
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.