Royal Decree of 18 April 2017 · Title 1 · General provisions

Article 7. Award Decree

Chapter 2. – Estimation of the amount of the contract

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The estimated value of a contract is calculated on the basis of the total amount payable, exclusive of value added tax, as estimated by the contracting authority. The estimate takes account of the duration and the total value of the contract and in particular of the following elements:

1° all required or permitted options;

2° all lots;

3° all repetitions as referred to in Article 42, § 1, 2°, of the Act;

4° all fixed and conditional parts of the contract;

5° all premiums or payments provided for by the contracting authority for the benefit of candidates, participants or tenderers;

6° where applicable, the revision provisions;

7° the extensions.

§ 2 Where a contracting authority consists of separate operational units, the estimated total value of the contracts of all the operational units is taken into consideration.

Notwithstanding the first paragraph, where a separate operational unit is independently responsible for its public contracts or for certain categories thereof, the values may be estimated at the level of each operational unit.

§ 3 The choice of the method for calculating the estimated value of a public contract may not be intended to exclude the contract from the publication rules. Nor may a public contract be split in order to exclude the contract from the publication rules, unless objective reasons justify this.

§ 4 The estimated value is valid at the time at which the contract notice is sent or, in cases where no such notice is provided for, at the time at which the award procedure begins for the contracting authority, for example, at the time at which the procurement documents are sent.

§ 5 In calculating the value of a framework agreement and of a dynamic purchasing system, the basis is the estimated maximum value, exclusive of value added tax, of all the contracts envisaged for the total duration of the framework agreement or the dynamic purchasing system.

§ 6 In calculating the value of an innovation partnership, the basis is the estimated maximum value, exclusive of value added tax, of the research and development activities that will take place in all stages of the envisaged partnership, as well as of the supplies, services or works that will be developed and acquired.

§ 7 In the case of public works contracts, the calculation of the estimated value takes into account the cost of the works, as well as the estimated total value of the supplies and services that are made available to the contractor by the contracting authority, if these are necessary for the execution of the works.

§ 8 In the case of public supply or service contracts that are awarded at regular intervals or that are intended to be renewed within a given period, the following basis is taken for calculating the estimated value of the contract:

1° either the total actual value of the successive similar contracts awarded during the preceding financial year or during the preceding twelve months, where possible adjusted for anticipated changes in quantity or value during the twelve months following the first contract;

2° or the total estimated value of the successive contracts awarded during the twelve months following the first supply, or during the financial year where that extends to more than twelve months.

§ 9 In the case of public supply contracts relating to the leasing, rental or hire purchase of products, the following basis is taken for calculating the estimated value of the contract:

1° in the case of public contracts of a fixed duration, the total estimated value for the entire term if that is no more than twelve months, or otherwise the total value if the term exceeds twelve months, including the estimated residual value;

2° in the case of public contracts of indefinite duration or whose term cannot be determined, the monthly amount payable multiplied by forty-eight.

§ 10 The estimate of service contracts includes the total remuneration of the service provider.

The following are taken into account for the calculation of this amount:

1° insurance services: the premium payable and other forms of remuneration;

2° banking and other financial services: fees, commissions and interest payable, as well as other forms of remuneration;

3° contracts relating to a design: fees, commissions and other forms of remuneration payable.

§ 11 In the case of public service contracts for which no total price is stated, the following basis is taken for calculating the estimated value of the contract:

1° in the case of contracts with a fixed term that is equal to or shorter than forty-eight months: the total value for the entire term;

2° in the case of contracts of indefinite duration or whose term is longer than forty-eight months: the monthly value multiplied by forty-eight.

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.