Almost every choice in an award procedure depends on one amount: the estimated value of the contract. It decides whether the contract must be published at European level, which procedures are available and which time limits and remedies apply.

The duty to estimate

The value of the contract must be estimated; the King sets how (Article 16). Every amount in the Act is, unless otherwise provided, an amount net of VAT (Article 16, second paragraph). The estimate made when the procedure is launched decides the rules that apply throughout it, in so far as those rules depend on the estimated value (Award Decree, Article 6). It is valid at the moment the contract notice is sent or, where there is no notice, when the procedure begins (Award Decree, Article 7, § 4).

What the estimate must include

The estimated value is the total amount payable, net of VAT, taking into account the duration and the total value of the contract (Award Decree, Article 7, § 1), and in particular:

For a framework agreement what counts is the estimated maximum value of all the contracts envisaged for its total duration (Award Decree, Article 7, § 5). For services with no total price, with a term of forty-eight months or less, the total value for the whole term counts; with an indefinite or longer term, the monthly value multiplied by forty-eight (Award Decree, Article 7, § 11). For regular or renewable supplies and services the bases of Award Decree, Article 7, § 8 apply.

No splitting

The method of calculation may not be chosen to take the contract outside the publication rules, and a contract may not be split to do so, unless objective reasons justify it (Award Decree, Article 7, § 3).

The European thresholds

From these amounts European publication is compulsory (Award Decree, Article 11):

ContractThresholdBasis
WorksEUR 5,404,000Award Decree, Article 11, 1°
Supplies and services of the federal contracting authorities of Annex 2, Part AEUR 140,000Award Decree, Article 11, 2°
Supplies and services of the other contracting authoritiesEUR 216,000Award Decree, Article 11, 3°
Social and other specific servicesEUR 750,000Award Decree, Article 11, 4°

The competent minister adjusts the first three amounts after the European revisions (Award Decree, Article 11, second paragraph). Lots have an exception: see the guide on lots and framework agreements.

The Belgian amounts

Below the European thresholds other amounts decide what is allowed:

Every amount with its source is on the thresholds page. Which procedure goes with which amount is in the guide on the award procedures.