Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 12. Subcontractors
Section 1. – General framework
§ 1 The contractor remains liable towards the contracting body where it entrusts the performance of its obligations in whole or in part to third parties. The contracting body has no contractual relationship whatsoever with those third parties.
§ 2 In the following cases the contractor must have recourse to one or more predetermined subcontractors:
1° where, for its qualitative selection in connection with the criteria relating to educational and professional qualifications, or to relevant professional experience, the contractor has relied on the capacities of predetermined subcontractors in accordance with Article 73, § 1, of the royal decree for the classical sectors, Article 72 of the royal decree for the special sectors or Article 79 of the royal decree for defence and security, as the case may be;
2° where the contracting body imposes the use of certain subcontractors on the contractor.
The use of other subcontractors is subject to the prior consent of the contracting body.
Only in the case referred to in the first paragraph, under 2°, is the contracting body responsible for the financial and economic capacity and the technical and professional ability of the subcontractor(s) concerned.
§ 3 Where the contractor has proposed certain subcontractors in its tender in accordance with Article 74 of the royal decree for the classical sectors, Article 73 of the royal decree for the special sectors or Article 140 of the royal decree for defence and security, as the case may be, the former, where it makes use of subcontracting in the performance, may in principle have recourse only to the proposed subcontractors concerned, unless it obtains the consent of the contracting body to use another subcontractor.
The first paragraph does not apply where the contracting body, in accordance with Article 12/2, has requested the replacement of the subcontractor(s) concerned because they are in a situation giving rise to an exclusion ground.
§ 4 Where it concerns a public works contract, the contracting body refers in the procurement documents to the direct action of the subcontractor in accordance with Article 1798 of the Civil Code.
Amended byKB 2017-06-22/01, art. 12 (in force 30-06-2017)
Previous article
11 — Supervising official
Next article
12/1 — Where it concerns a contract in a fraud-prone sector, the contractor shall, at…
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.