Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts

Article 12/3. Performance Decree

Section 1. – General framework

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 A subcontractor is prohibited from subcontracting the whole of the contract awarded to it to another subcontractor. A subcontractor is likewise prohibited from retaining only the coordination of the contract.

§ 2 Without prejudice to Article 2, § 3bis, of the Act of 10 April 1990 regulating private and special security, the subcontracting chain for contracts in a fraud-prone sector awarded by contracting authorities is limited as follows:

1° where it concerns a works contract which, by its nature, is classified in a category in accordance with Article 4 of the Royal Decree of 26 September 1991 laying down certain measures for the implementation of the Act of 20 March 1991 regulating the accreditation of works contractors, the subcontracting chain may consist of no more than three levels, namely the direct subcontractor of the contractor, the second-level subcontractor and the third-level subcontractor;

2° where it concerns a works contract which, by its nature, is classified in a subcategory in accordance with Article 4 of the aforementioned Royal Decree of 26 September 1991, the subcontracting chain may consist of no more than two levels, namely the direct subcontractor of the contractor and the second-level subcontractor;

3° where it concerns a service contract in a fraud-prone sector, the subcontracting chain may consist of no more than two levels, namely the direct subcontractor of the contractor and the second-level subcontractor.

Without prejudice to Article 78/1, one additional level of subcontracting is, however, possible in the following cases:

1° where circumstances arise that could not reasonably have been foreseen when the tender was submitted, that could not be avoided and the consequences of which could not be remedied by the economic operators, notwithstanding that everything necessary was done to that end, and in so far as these circumstances are notified in writing to the contracting authority within thirty days after they have arisen; or

2° subject to the prior written agreement of the contracting authority.

Where it concerns a works contract and the contractor requests the agreement of the contracting authority referred to in the second paragraph, 2°, it shall attach a certificate showing that the subcontractor concerned holds the accreditation. Failing that, it shall provide a copy of the decision referred to in Article 6 of the Act of 20 March 1991 regulating the accreditation of works contractors that the subcontractor concerned meets the accreditation conditions or the requirements regarding equivalence of an accreditation. The contracting authority shall verify this certificate or this decision.

The following are not regarded as subcontractors for the purposes of this Article:

1° the parties to a combination without legal personality, including the temporary commercial partnership;

2° suppliers of goods, without additional placement or installation works;

3° the bodies or institutions that carry out inspection or certification;

4° temporary employment agencies within the meaning of the Act of 24 July 1987 on temporary work, agency work and the placing of workers at the disposal of users.

§ 3 Without prejudice to the possibility of applying ex officio measures, any failure to comply with this Article gives rise to the application of a penalty that is daily and amounts to 0.2 per cent of the original contract amount. This penalty is applied from the fifteenth day after the date of dispatch of the registered mail or the electronic mail that likewise guarantees the exact date of dispatch, referred to in Article 44, § 2, and runs up to and including the day on which the infringement has been brought to an end.

The penalty referred to in the first paragraph may, however, never exceed:

a) EUR 5,000 per day where it concerns a contract whose original contract price is lower than EUR 10,000,000;

b) EUR 10,000 per day where it concerns a contract whose original contract amount is equal to or higher than EUR 10,000,000.

Amended byIngevoegd bij KB 2017-06-22/01, art. 13 (in force 30-06-2017) · KB 2018-04-15/01, art. 8 (in force 28-04-2018)

Cross-references

This article refers to