Royal Decree of 14 January 2013 · Title 5 · Specific provisions for public supply contracts
Article 124. Measures taken of its own motion
Section 1. – Common provisions for all supply contracts
§ 1 Where measures are taken of the contracting body's own motion in the form of performance in-house or of a contract for the account of the defaulting party, the additional costs are calculated exclusively on the deliveries that the defaulting supplier was bound to carry out and that were actually carried out in-house or ordered from the new supplier, without taking into account the price revisions referred to in Article 38/7, § 2, or the reductions for loss of value referred to in Article 71 of this Decree, which could have altered the prices of the defaulting supplier or of the new supplier. The prices that are taken into account for the calculation of the additional costs are, where applicable, increased by value added tax.
Penalties for delay continue to run at the expense of the supplier who has been put in default until the date of delivery or production and, in the case of a contract for the account of the defaulting party, at the latest until the expiry of the period for performance of the contracting body's own motion.
§ 2 Where the contract relates to deliveries that are no longer or not available on the market or that could have been supplied only by the supplier in default, and where the contracting body cannot possibly obtain identical goods, it may, after formal notice by registered mail or by electronic means that guarantee the exact date of dispatch in a comparable manner, replace them with similar goods, under the conditions referred to in Article 47 and in § 1 of this Article.
In the formal notice, the contracting body specifies the similar deliveries that it intends to order.
§ 3 Deliveries for the account of the supplier in default are inspected and accepted in accordance with the requirements of the original contract.
In the case referred to in § 2, deliveries of the same kind ordered for the account of the supplier in default or carried out in-house are subjected to the tests determined by the contracting body.
The supplier that has defaulted is duly notified of the place where and the date on which the tests referred to in the two preceding paragraphs will be carried out. It may be present or be represented there, unless the new supplier objects to this where the inspection operations have to take place on its premises. In that case the supplier in default may demand communication of the result of the inspection and of the acceptance.
§ 4 The supplier put in default also bears the costs of concluding the contract or contracts for its account. Regardless of the method of award used for the contract, these costs are set at one per cent of the original contract sum of that contract, with a maximum of fifteen thousand euro.
Amended byKB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2017-06-22/01, art. 45 (in force 30-06-2017)
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.