Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 Where the contractor, after the expiry of the period laid down in Article 44, § 2, for putting forward his defence, has remained inactive or has put forward arguments which the contracting body considers unjustified, the latter may take the ex officio measures set out in paragraph 2.

The contracting body may nevertheless take the ex officio measures without awaiting the expiry of the period referred to in Article 44, § 2, where the contractor has explicitly admitted the breaches found in advance.

§ 2 The ex officio measures are:

1° unilateral termination of the contract, in which case the contracting body, except in the case referred to in Article 49, first paragraph, 1°, acquires by operation of law the entire surety as liquidated damages or, in the absence of a surety, an equivalent amount. This measure excludes the application of any penalty for delay on the part to which the termination relates;

2° performance in-house of all or part of the unperformed contract;

3° the conclusion of one or more contracts on behalf of and at the expense of one or more third parties for all or part of the contract still to be performed.

The measures under the first paragraph, 2° and 3°, are taken at the expense and risk of the defaulting contractor. Nevertheless, the penalties for delay and penalties applied in the performance of a contract concluded at the defaulting contractor's expense are borne by the new contractor.

§ 3 The decision of the contracting body to proceed with the chosen ex officio measure shall be notified to the defaulting contractor by registered mail or by electronic means which similarly guarantees the exact date of dispatch.

From this notification, the defaulting contractor may no longer intervene in the performance of the part of the contract subject to the ex officio measure.

Where a contract is concluded at the defaulting contractor's expense, a copy of the procurement documents relating to the contract to be concluded shall be sent to the defaulting contractor by registered mail or by electronic means which similarly guarantees the exact date of dispatch.

§ 4 Where the price of the in-house performance or that of the new contract concluded at the defaulting contractor's expense is higher than that of the original contract, the defaulting contractor shall bear the additional costs. In the opposite case, the difference benefits the contracting body.

Amended byKB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2017-06-22/01, art. 25 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.