Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 38/1. Additional works, supplies or services
Section 5. – Modifications of the contract
A modification may be made without a new award procedure for additional works, supplies or services to be carried out by the original contractor that have become necessary and that were not included in the original contract, where a change of contractor:
1° cannot be made for economic or technical reasons, such as where the additional goods or services must be interchangeable or interoperable with existing equipment, services or installations acquired under the original contract; and
2° would cause significant inconvenience or a significant increase in costs for the contracting body.
The price increase resulting from the modification may not, however, exceed fifty per cent of the value of the original contract. Where several successive modifications are made, this limit applies to the value of each modification. Such successive modifications may not be used to circumvent the legislation on public procurement. This paragraph does not apply to contracts awarded by contracting entities pursuing activities in the water, energy, transport and postal services sectors as referred to in Title III of the Act.
For the calculation of the amount referred to in the second paragraph, where the contract contains an indexation clause, the updated value is used as the reference value.
Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)
Previous article
38 — The revision clause
Next article
38/2 — Unforeseeable circumstances on the part of the contracting body