Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts

Article 38/2. Unforeseeable circumstances on the part of the contracting body

Section 5. – Modifications of the contract

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

A modification may be made to a contract without a new award procedure where each of the following conditions is met:

1° the modification is the necessary consequence of circumstances that a diligent contracting body could not foresee;

2° the modification does not change the overall nature of the contract or framework agreement;

3° the price increase resulting from a modification does not exceed fifty per cent of the value of the original contract or framework agreement. Where several successive modifications are made, this limit applies to the value of each modification. Such successive modifications may not be used to circumvent the legislation on public procurement.

The condition stated in the first paragraph, 3°, does not apply to contracts awarded by contracting entities pursuing activities in the water, energy, transport and postal services sectors as referred to in Title 3 of the Act.

For the calculation of the amount referred to in the first paragraph, 3°, where the contract contains an indexation clause, the updated value is used as the reference value.

Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.