Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 51. Performance Decree
Section 7. – Remedies of the contracting body
The contractor obtains partial reimbursement of the penalties in the event of a disproportion between the amount of the penalties applied and the extent of the defective performance.
This reimbursement is subject to the condition that the contractor has done everything in his power to remedy the defective performance as quickly as possible.
On pain of forfeiture, every application for reimbursement of the penalties shall be submitted in writing, within the periods laid down in Article 50, § 3.