Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts

Article 50. Reimbursement of penalties for delay and penalties

Section 7. – Remedies of the contracting body

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The contractor obtains reimbursement of the penalties for delay imposed:

1° in whole or in part where he proves that the delay is wholly or partly attributable either to the contracting body or to the circumstances referred to in Article 38/9, § 1, insofar as these occurred before the expiry of the contractual periods, in which cases interest shall be paid by operation of law on the reimbursed penalties, from the date on which the payment concerned was due, at the interest rate laid down in Article 69;

2° in part, where there is a disproportion between the penalties and the minor importance of the services performed late. This disproportion is deemed to exist where the value of the unperformed services does not reach five per cent of the total amount of the contract, provided that the services performed can nevertheless be used normally and the contractor has done everything in his power to complete the late services in the shortest possible time.

§ 2 The conditions for submission referred to in Article 38/15 apply to the facts and circumstances invoked in the applications for reimbursement of the penalties for delay referred to in § 1, 1°.

§ 3 On pain of forfeiture, every application for reimbursement of penalties shall be submitted in writing, no later than ninety days counting from:

1° the sole payment or the payment declared as the balance, as regards works contracts;

2° the payment of the invoice from which the penalties were withheld, as regards supply and service contracts.

Amended byKB 2014-02-07/10, art. 70 (in force 03-03-2014) · KB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2017-06-22/01, art. 28 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.