Article 70. Interruption or slowing down of performance by the contractor
Section 11. – General payment conditions
Where, through the fault of the contracting body, payment has not been made after thirty days have elapsed since the expiry of the processing period, the contractor may slow down or interrupt the pace of performance of the works, supplies or services.
In this case, the contractor is entitled:
1° in any event, regardless of whether there is a slowing down of the pace of performance or an interruption, to an extension of the period equal to the number of days between the expiry of the aforementioned period of thirty days and the date of payment, provided that the request is submitted in writing before the expiry of the contractual periods;
2° to damages, if there has actually been a slowing down of the pace of performance or an interruption and provided that the claim for damages is submitted within the periods laid down in Article 38/16.
The decision to slow down the pace of performance or to interrupt the works, supplies or services on account of arrears of payment must, however, be notified to the contracting body by registered mail or by electronic means which similarly guarantees the exact date of dispatch, at the latest fifteen days before the day of the slowing down of the pace of performance or of the actual interruption.
Where several overruns of processing periods overlap, they may be taken into account only once.
The provisions of this Article may be invoked only on condition that this is justified by the amount of the overdue payments in the course of the period in question.
Amended byKB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017) · KB 2017-06-22/01, art. 34 (in force 30-06-2017) · KB 2024-08-12/15, art. 7 (in force 01-01-2025)
Previous article
69 — Interest for late payment and compensation for recovery costs
Next article
71 — Reduction on account of lesser value
Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.