Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts
Article 38/16. Performance Decree
Section 5. – Modifications of the contract
The contractor requesting the application of one of the revision clauses referred to in Articles 38/8 to 38/9, 38/11 and 38/12 must, on pain of forfeiture, submit the itemised justification of his request in writing to the contracting body within the following periods:
1° before the expiry of the contractual periods, in order to obtain an extension of the period or the termination of the contract;
2° no later than ninety days following the date of notification to the contractor of the report of provisional acceptance of the contract, in order to obtain a revision of the contract other than that referred to in 1° or damages;
3° no later than ninety days after the expiry of the guarantee period, in order to obtain a revision of the contract other than that referred to in 1° or damages, where this request for application of the revision clause originates in facts or circumstances that occurred during the guarantee period.
Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)
Previous article
38/15 — The contractor may rely on the application of one of the revision clauses…
Next article
38/17 — The contracting body must, no later than ninety days following the date of…