Article 79. Organisation of the construction site

Section 1. – Provisions applicable to all works contracts

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

Without prejudice to the legislation on the well-being of employees in the performance of their work, the contractor is responsible for order on the construction site for the duration of the works, and is obliged, in the interest of the officials of the contracting body and of third parties as well as of his own staff, to take all necessary measures to guarantee their safety.

The contractor shall, on his full responsibility and at his expense, take all the measures that are indispensable for the protection, preservation and integrity of the existing structures and works. He shall also take all precautions required by the art of building and by the particular circumstances in order to safeguard neighbouring properties and to avoid disturbances being caused to them through his fault.

Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.