Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 80. Modifications to the contract
Section 1. – Provisions applicable to all works contracts
§ 1 Every order to modify the contract shall be given in writing. An oral order is, however, treated as equivalent to a written order where the contractor has reported it to the supervising official within forty-eight hours by registered mail or by electronic means which similarly guarantees the exact date of dispatch, and where it has not been refuted by the contracting authority within three working days from receipt of the said letter.
Less important modifications may, however, be recorded merely as entries in the journal.
The orders or the entries indicate the modifications to be made to the original provisions of the contract and to the plans.
§ 2 Unforeseen works which the contractor is bound to carry out, foreseen works that are withdrawn from the contract, and all other modifications are calculated at the unit prices of the tender or, failing that, on the basis of unit prices to be agreed.
In either of the following cases, each party may demand a revision of the unit prices for additional works of the same nature and described in the same terms as in the item of the bill of quantities:
1° the additional works exceed three times the quantity provided for in the item concerned of the bill of quantities;
2° the price of the supplements relating to the item concerned exceeds ten per cent of the contract amount, with a minimum of two thousand euro.
If a new unit price is agreed for an additional work, the old price remains applicable to the quantity initially indicated.
Each party may likewise demand a revision of the unit prices where the quantity withdrawn from an item of the bill of quantities amounts to more than one fifth of the quantity initially indicated.
§ 3 For there to be grounds for revision of unit prices, one of the parties must make its wish in that regard known to the other party by registered mail or by electronic means which similarly guarantees the exact date of dispatch, within a period of thirty days from the date on which the modification orders were validly given.
In the absence of agreement on the new unit prices, the contracting body shall fix them ex officio, without prejudice to all rights of the contractor.
The contractor is obliged to continue the works without interruption, despite the disputes to which the fixing of new prices might give rise.
§ 4 In the case of additional works or modifications to the foreseen work, the written order, the adjustment statement or the rider states:
1° either the extension of the performance period on the basis of the increase in the amount of the contract and of the nature of the modifications and the additional works;
2° or the exclusion of any extension of the period.
§ 5 Where the modifications ordered by the contracting body lead to one or more adjustments which together cause a reduction of the original contract sum, the contractor is entitled to a fixed compensation of ten per cent of this reduction, regardless of the final amount of the contract.
Payment of this compensation is subject to the contractor submitting a claim or a written request that takes its place.
Amended byKB 2014-05-22/03, art. 3 (in force 09-06-2014; zie ook KB 2014-05-22/03, art. 21) · KB 2017-06-22/01, art. 2 (in force 30-06-2017)
Previous article
79 — Organisation of the construction site
Next article
81 — Fluctuation of the estimated quantities