Article 84. Liability of the contractor

Section 1. – Provisions applicable to all works contracts

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 The contractor is liable for all works carried out by him or by his subcontractors until final acceptance of all the works.

During the guarantee period, the contractor must, as required, carry out on the construction all the works and repairs necessary to keep it in good condition or in good working order.

After provisional acceptance, the contractor is, however, not liable for damage for which he is not at fault.

§ 2 From provisional acceptance and without prejudice to the provisions of paragraph 1 concerning his obligations during the guarantee period, the contractor is liable for the solidity of the construction and for the proper performance of the works, in accordance with Articles 1792 and 2270 of the Civil Code.

Cross-references

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.