Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 85. Presumption of fraud or poor workmanship
Section 1. – Provisions applicable to all works contracts
Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.
If fraud or poor workmanship is suspected, the contractor may be obliged to demolish and rebuild the work performed in whole or in part. The costs of demolition and rebuilding are borne, depending on whether the suspicion proves true or not, by the contractor or by the contracting body.
Amended byKB 2017-06-22/01, art. 2 (in force 30-06-2017)
Cross-references
Referred to by