Royal Decree of 14 January 2013 · Title 3 · Specific provisions for public works contracts
Article 86. Penalties for delay
Section 1. – Provisions applicable to all works contracts
§ 1 Penalties for delay are calculated on the basis of the formula:
R = 0.45 x ((M x n) / N)
in which:
R = the amount of the penalty to be applied;
M = the original contract amount;
N = the number of working days laid down for performance at the start of the contract;
n = the number of days of delay.
Where, however, the factor M does not exceed seventy-five thousand euro while N is not greater than one hundred and fifty days, the denominator N is replaced by 150 x N.
§ 2 If the performance period is an award criterion of the contract, the method of calculating the penalties for delay is laid down in the procurement documents. Otherwise, the formula of paragraph 1 applies.
§ 3 Where the performance period is not expressed in working days, the number N in the formula is obtained conventionally by multiplying the number of days of the performance period by 0.7. The product obtained is rounded down.
§ 4 Where the contract consists of several parts or phases, each with its own performance period N and its own amount M, each of the parts is treated as a separate contract for the application of the penalties.
§ 5 If the contract does not consist of parts or phases within the meaning of paragraph 4, but the procurement documents lay down partial performance periods without these being binding, those periods must be regarded as merely indicative for the performance of the contract and, for the application of the penalties, only the final period is taken into account. If, on the other hand, the procurement documents state that the partial performance periods are mandatory, failure to observe them is penalised by special penalties provided for that purpose in those documents or, if there is no such provision, by penalties calculated according to the formula referred to in paragraphs 1 and 2, in which the factors M and N relate to the whole contract. The highest penalty for each partial performance period of P working days is, however:
(M / 20) x (P / N)
If a partial performance period is not expressed in working days, paragraph 3 is applied.
§ 6 The total amount of the penalties for delay applied to a contract may not exceed five per cent of the amount M, as determined in paragraph 1. Where the performance period is an award criterion of the contract, the procurement documents may increase the above-mentioned percentage to a maximum of ten per cent. This percentage is fixed in proportion to the relative importance of the award criterion concerning the performance period.
Penalties whose total does not reach seventy-five euro per contract are not charged.