Act of 17 June 2013 · Title III · Reasoning, information and remedies for public contracts falling under the Defence and Security Act
Article 35. Remedies Act
Chapter 1. – Contracts that reach the European thresholds — Section 1. – Scope
This Chapter applies to the contracts and qualification systems that reach the amount for European publication set by the King, and that fall under the Defence and Security Act.
As regards the defence contracts referred to in Article 346(1)(b) of the Treaty on the Functioning of the European Union and the contracts excluded on the basis of essential security interests, however, only Articles 36, 37, 39 to 42, 46 to 48 and 55 to 59 apply.
...
Where the initial estimate of the contract or of the concession is lower than the amount set for European publication, but the amount of the tender to be approved, excluding value added tax, is more than 20 % higher than that set amount, this Chapter applies, with the exception of Article 36, first paragraph, 1° to 5°, second and third paragraphs, and Article 39, and on the understanding that this application is preceded by the application of Chapter 2. This paragraph does not apply in the case provided for in Article 44, 1°.
Amended byW 2013-12-04/10, art. 4 (in force 20-12-2013) · W 2017-02-16/19, art. 4 (in force 30-06-2017) · W 2017-02-16/19, art. 46 (in force 30-06-2017)
Previous article
34 — The European Commission may use the procedure referred to in §§ 2 to 5 where it…
Next article
36 — The contracting body shall draw up a reasoned decision…