Article 55. Remedies Act

Chapter 1. – Contracts that reach the European thresholds — Section 5. – Review procedures — Subsection 6. – Time limits for review

Text of the consolidated version in force from 1 January 2026, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

§ 1 Review procedures shall be brought, on pain of inadmissibility, within the time limits referred to in §§ 2 to 4, 5, first paragraph, and 6, from the publication, the notification or the taking of cognisance of the legal act, as the case may be.

Where this Act imposes an obligation to communicate, in the event of non-simultaneous dispatches, the time limits shall start to run from the day of the last dispatch. In any event, the time limits shall start to run only in so far as the reasons have been communicated.

§ 2 The action for annulment referred to in Article 46 shall be brought within a time limit of sixty days, without prejudice to Article 41/1, § 2, second paragraph.

§ 3 The action for suspension referred to in Article 47 shall be brought within a time limit of fifteen days. Where Article 50 is applied, the time limit is ten days.

§ 4 Without prejudice to the provisions applicable to compensatory damages referred to in Article 11bis of the Acts on the Council of State, coordinated on 12 January 1973, the action for damages referred to in Article 48 shall be brought within a time limit of five years.

§ 5 The action for a declaration of ineffectiveness referred to in Article 49 shall be brought within a time limit of thirty days starting on the day after the contracting body, either:

1° has published the contract award notice in accordance with the provisions laid down by the King, where the contracting body has decided to award this contract without prior publication of a notice in the Official Journal of the European Union and the Bulletin der Aanbestedingen and the contract award notice contains the justification for this decision, or

2° has informed the candidates and tenderers concerned that the contract has been concluded and has at the same time communicated to them the reasoned decision concerning them.

The time limit for review is six months from the day after the conclusion of the contract where the contracting body does not comply with the provisions of the first paragraph.

§ 6 The action for alternative penalties referred to in Article 54 shall be brought within a time limit of six months.

Amended byW 2017-02-16/19, art. 57 (in force 30-06-2017)

Cross-references

This article refers to

Referred to by

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.