Practical guide
Time limits for tenders
The minimum time limits for requests to participate and for tenders in each procedure, when they may be shortened and when they must be extended.
Legal basisArticle 36, § 1, second paragraph · Article 36, § 2 · Article 36, § 3 · Article 36, § 4 · Article 37, § 1, second paragraph · Article 37, § 2, second paragraph · Article 37, § 3 · Article 37, § 4 · Article 37, § 5 · Article 38, § 3, third paragraph · Article 41, § 2, second paragraph · Article 64, § 1, third paragraph · Article 64, § 2 · official text
A tender takes time to prepare, and the Act sets, procedure by procedure, the least time a contracting authority must give. Each time limit runs from the date the contract notice or the invitation is sent. The time limits table lists each one with the provision it is read from, and the calculator counts one from a date.
The minimum time limits
| Procedure | Time limit | Basis |
|---|---|---|
| Open procedure | tenders: at least 35 days from the notice | Article 36, § 1, second paragraph |
| Restricted procedure | requests: at least 30 days from the notice | Article 37, § 1, second paragraph |
| Restricted procedure | tenders: at least 30 days from the invitation | Article 37, § 2, second paragraph |
| Competitive procedure with negotiation | requests and initial tender: at least 30 days each | Article 38, § 3, third paragraph |
| Competitive dialogue | requests: at least 30 days from the notice | Article 39, § 1, third paragraph |
| Innovation partnership | requests: at least 30 days from the notice | Article 40, § 1, fourth paragraph |
| Simplified negotiated procedure with prior publication | tenders: at least 22 days from the notice | Article 41, § 2, second paragraph |
The wording of Articles 36 and 37 makes no distinction by the estimated value of the contract.
Shorter after a prior information notice
Where the contracting authority has published a prior information notice, the time limit for tenders may be shortened to fifteen days in the open procedure (Article 36, § 2) and to ten days in the restricted procedure (Article 37, § 3). Two conditions apply: the prior information notice contained all the information the King requires, in so far as it was available at the time, and it was sent at least thirty-five days and at most twelve months before the contract notice (Article 36, § 2, 1°, Article 36, § 2, 2°). A prior information notice is compulsory only where the contracting authority wants to use that reduction (Award Decree, Article 15, § 2, Award Decree, Article 21, second paragraph).
Shorter for urgency
In a duly substantiated state of urgency the time limit in the open procedure may be no less than fifteen days (Article 36, § 3). In the restricted procedure: at least fifteen days for requests and at least ten days for tenders (Article 37, § 4).
Five days shorter for electronic submission
Where tenders are submitted by electronic means under the rules on electronic platforms, the time limit for tenders may be shortened by five days, in the open (Article 36, § 4) and in the restricted procedure (Article 37, § 5). The competitive procedure with negotiation and the simplified negotiated procedure refer to those rules of Article 37 (Article 38, § 3, third paragraph, Article 41, § 2, second paragraph).
When the time limit must be longer
- Where the procurement documents are not freely, fully, directly and free of charge available by electronic means, the time limit for tenders is extended by five days, except in duly substantiated urgent cases (Article 64, § 1, third paragraph).
- Additional information on the specifications must, if requested in good time, be provided no later than six days before the time limit for the receipt of tenders; in the accelerated procedure, four days (Article 64, § 2).
- Where the electronic platform is unavailable, the contracting authority may postpone the deadline: by at least six days below the European threshold and at least eight days at or above it (Award Decree, Article 57, § 1).
After the award
After the award decision, for contracts that reach the European thresholds, comes the standstill period of fifteen days before the contract is concluded (Remedies Act, Article 11). See the guide on the standstill period and remedies.
Related pages
Previous guide
Thresholds and the estimated value of the contract
Next guide
The standstill period and remedies