Article 38/13. Prohibition on delaying or interrupting performance
Section 5. – Modifications of the contract
The contractor may not rely on ongoing discussions on the application of one of the revision clauses referred to in Articles 38/9 to 38/12 in order to slow down the pace of performance of the contract or to interrupt performance of the contract or not to resume it, as the case may be.