Royal Decree of 14 January 2013 · Title 2 · Common provisions for public works, supply and service contracts

Article 38/11. Acts of the contracting body and of the contractor

Section 5. – Modifications of the contract

Text of the consolidated version in force from 1 January 2025, as Justel publishes it. Where they differ, the text published in the Belgian Official Gazette prevails: official textThe Dutch text is authentic (with the French and the German); the English is our unofficial translation, and the Dutch prevails. A page shows the text of its own language.

The procurement documents shall provide for a revision clause, as laid down in Article 38, in which the arrangements are determined for the revision of the conditions of the contract where the contracting body or the contractor has suffered a delay or a detriment as a result of negligence, delays or any acts whatsoever that can be attributed to the other party.

The revision referred to in the first paragraph may consist of one or more of the following measures:

1° the adjustment of the contractual provisions, including the extension or shortening of the performance periods;

2° damages;

3° termination of the contract.

Where the procurement documents do not contain a revision clause as referred to in the first paragraph, the arrangement contained in the second paragraph is deemed to apply by operation of law.

Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)

Cross-references

This article refers to

Want your tender documents checked before publication? We will show you how Procurelex Toetsing does it.

Request a demo

General information on the Public Procurement Act in force. Not legal advice.